ABB, Air Circuit Breakers, Digital Protection

ABB Emax 2: How Ekip Communication Changes the Way You Commission an ACB

Video cover — SACE Emax 2 + Ekip Connect — frame supplied by credited video publisher
VIDEO-FIRST ENGINEERING BRIEFING FAYYAZ / FIELD NOTES 02

[fayyaz_youtube id=”k1g_O3aFUb0″]

WATCH FIRST · Emax 2 — Basic Communication Commissioning via Ekip Connect · Publisher: ABB.

ABB / ENGINEERING IN PRACTICE

Commissioning is now a data task

An ACB commissioning problem often looks mechanical until the engineer discovers a communications setting, a missing module or an untested alarm map. ABB Emax 2 and the Ekip ecosystem deserve a workflow that treats protection and connectivity as two independent commissioning disciplines.

SACE Emax 2 + Ekip Connect product photo
ABB SACE Emax 2 breaker with Ekip display, representative unit. Manufacturer reference
THE TAKEAWAY

An ACB commissioning problem often looks mechanical until the engineer discovers a communications setting, a missing module or an untested alarm map. ABB Emax 2 and the Ekip ecosystem deserve a workflow that treats protection and connectivity as two independent commissioning disciplines. Practical selection guidance, wiring decisions and a test checklist.

01 / First separate protection from communications

Confirm that the actual Ekip trip-unit version supports the required protection curves and measurement functions. Inspect the breaker rating plate, withdrawable/fixed arrangement, trip-unit supply and selected accessory list. A Modbus mapping cannot solve an incorrect LSIG setting or a mismatched CT configuration.

02 / What Ekip Connect changes

The ABB manufacturer tutorial demonstrates basic communication commissioning using Ekip Connect. The practical value is repeatability: parameter files, readable device information and diagnostic checks. The workstation still requires correct software version, interface and connection method. Record the exact software package used in the FAT report.

03 / Make the SCADA point list useful

Do not import every Modbus register just because it exists. Start with status, trip cause, protection active, electrical measurements and communication health. Give alarms severity levels and retain trip history with event time. Test a simulated or safely initiated communication loss and verify that the SCADA graphic clearly distinguishes a stopped connection from a healthy open breaker.

04 / Safe test sequence in the workshop

With switching sources isolated and the panel under an approved FAT procedure, inspect mechanical interlocks, open/close circuits and spring charged/ready states. Validate control supply polarities, fuse protection and the location of test points. Use ABB-approved test devices and procedures for the trip-unit protection tests; simulated software status alone is not proof of a physical trip.

05 / Is the upgrade worthwhile?

For complex ATS and plant distribution, structured event and fault data can shorten troubleshooting and support preventive maintenance. The extra cost only creates value when engineers establish data ownership, backup records and proper commissioning documentation. Train operations to recognize real Ekip alarms rather than reset faults repeatedly.

ENGINEER’S REFERENCE TABLE

Core productABB SACE Emax 2 family
Digital ecosystemEkip trip units and supported communication modules
Commissioning softwareABB Ekip Connect, by compatible release
Practical handoverProtected settings backup and SCADA point list

FAT / COMMISSIONING: WHAT TO VERIFY

  1. Verify the exact Ekip trip-unit model and protection-function set.
  2. Confirm auxiliary power and communications accessory wiring.
  3. Record and sign the protection settings before energization.
  4. Exercise trip/alarm/status readback separately.
  5. Archive configuration and FAT test results.

Technical sources and video credits

Independent FAYYAZ Electric technical analysis; figures and options vary with the exact device part number and firmware. This article is not a manufacturer installation procedure.